How to estimate a translation deadline you can actually meet
How to estimate a translation deadline from your real throughput, file prep and review time, so the delivery date you promise is one you can hold.

Most late deliveries we hear about were not caused by slow translating. They were caused by a date agreed in ninety seconds, from a word count and a feeling, before anyone had opened the file. If you want to estimate a translation deadline you can actually meet, the arithmetic has to cover everything that happens between the file landing in your inbox and the file leaving it. Very little of that is translation.
This is the part of freelance planning nobody teaches. Rates get discussed endlessly. Turnaround gets a shrug and a guess. What follows is the method we see working: separate effort from calendar, measure your own throughput instead of borrowing an average, count the steps that are not translating, and put the buffer where the risk actually sits.
Why you cannot estimate a translation deadline from a word count alone
A word count answers one question. How much text is there. It says nothing about how hard the text is, what condition the file is in, or whether you have the hours free this week.
Two files at 4,000 words can be a day apart. A supply agreement with sixty numbered clauses, defined terms that have to match across the whole document, and cross-references that break if anything gets renumbered reads slowly and reviews even more slowly. Four thousand words of product blurbs for a website reads fast and reviews in an hour.
Format moves the number too. An XLSX workbook with 4,000 words spread across 900 cells in eleven sheets is not a 4,000-word document. Each cell is a fragment with no sentence around it, so you keep checking the neighbouring column to work out what a label refers to, and you are being careful not to touch the lookup values other sheets depend on. We routinely see that kind of workbook eat the same hours as a 7,000-word DOCX. PPTX does something similar. The deck has the slide text and the speaker notes, and the notes are often where a third of the words live and where nobody looks when quoting.
Then there is file condition. A clean DOCX import straight out of Word is one thing. A DOCX that someone produced by exporting a PDF, with every visual line as its own paragraph and the tables rebuilt as floating text boxes, is an hour of repair before any translating starts.
So the word count is the first input, not the estimate. It tells you the size of the job. The schedule comes from what you do with it.
Effort hours and calendar days are two different numbers
The most common mistake is collapsing these into one. You work out that a job takes fourteen hours, decide fourteen hours is roughly two days, and promise the day after tomorrow. Then Tuesday has a two-hour call, Wednesday morning goes to a rush job for a client you cannot refuse, and the fourteen hours spread themselves across four days.
Effort is how many working hours the job consumes. Calendar is where those hours exist in your actual week. You need both, and the second one is the one almost nobody writes down.
Write down how many productive translation hours your week really contains. Not forty. For most freelancers we talk to it sits somewhere between twenty and thirty, once email, quoting, invoicing, admin and the hours when your brain is not usable come out. Then subtract what is already committed. If you have twenty-five productive hours and fifteen are booked, you have ten. A fourteen-hour job does not fit this week, however optimistic Monday morning feels.
Calendar also carries the dead time you do not control. A terminology question sent Friday at six in the evening is a Monday answer. A client eight hours ahead of you gives you one exchange per day, not three. If the job needs two rounds of questions, that is two days of waiting built into the schedule before you have translated anything.
Keeping the two numbers visibly separate is what makes this work. Effort tells you what to charge. Calendar tells you what date to say out loud.
Measure your own throughput instead of borrowing an average
Published per-day figures are averages across everything: easy and hard, from scratch and post-edited, your language pair and pairs that behave nothing like it. They are a sanity check, not a planning input. We went through where those numbers come from in how many words a translator can translate per day, and the honest summary is that the spread is too wide to predict one specific file.
Your own log is better and takes a month to build. For each job, record six things: date, document type and format, language direction, source word count, whether you translated from scratch or post-edited AI output, and the clock hours from opening the file to sending it. Keep the review hours separate from the translation hours. They behave differently and they scale differently.
After fifteen or twenty jobs you stop guessing. You end up with something like: technical DOCX, full post-editing, 1,000 to 1,200 words an hour. Marketing copy from scratch, 450 words an hour, slower when the brand voice is fussy. Workbook cells, 350 to 400 words an hour. Those ranges are yours, and they are the only ones that predict your Thursday.
Use the bottom of the range, not the middle. An estimate built on your best observed speed assumes every day is a good day.
This does not apply cleanly if your work is genuinely one-off, a different domain and format and client every time, with no two jobs alike. Log the hours anyway, but lean harder on the next section, because in that situation your variability lives almost entirely in the non-translation steps.
Count the steps that are not translating
Translating is one line item in a job with eight. When an estimate goes wrong, it is rarely because the translation took longer than expected. It is because something else did and was never counted.
The full sequence usually runs:
- intake and triage, which means opening the file, checking what you actually received, and counting it properly rather than trusting the count you were sent
- file preparation: PDF conversion, table rebuilds, tag and placeholder cleanup, protecting the cells in a workbook that must not be translated
- reference setup: assembling a glossary, importing TM, reading whatever style guide exists
- the query round, both writing the questions and waiting for answers
- translation or post-editing
- the QA pass and the fixes it generates, which includes reading a QA report and acting on the real flags instead of clicking through them
- the formatting pass after translation, because the target text is a different length than the source and both DOCX and PPTX will show it
- delivery: naming, packaging, the cover note
Two of those get skipped almost every time. The query round, because waiting feels free until it costs two days. And the fix loop after QA, because people budget for checking and not for repairing what the checking found.
One figure worth testing against your own log: across the jobs we see, translation itself accounts for somewhere between half and two thirds of the total hours. Everything else is the remainder. If your estimate comes only from your words-per-hour rate, you have priced roughly 60% of the job and promised a date to match.
Put the buffer where the risk actually is
Padding everything by 20% is better than nothing and worse than thinking. A flat percentage buys a little room on the jobs that were never going to slip, and nowhere near enough on the one that was.
Name the single most likely thing to go wrong on this specific file, and buffer that instead. On most jobs it is the query round, so the buffer is a day of waiting, not a day of translating. On a scanned source it is the conversion, so the buffer goes at the front and you do not promise a date until you have seen what the OCR produced. On a job that ends in client review it is the review window, which you do not control at all.
Then keep two dates. The internal date is when you plan to finish. The client date is what you promised. The gap between them should be at least one night of sleep, because the review you do on a file you have not looked at for twelve hours catches things the review you do at eleven at night does not.
One habit we would push back on: quiet padding. If you add three days, deliver early every time and say nothing, the client learns your dates have three spare days in them and starts asking for the earlier one. State the date with its assumption attached instead. "Thursday at five, assuming the terminology answers come back by Tuesday midday" is a date you can hold, and it moves honestly when the assumption fails. That conversation is far easier before the work starts than after, which is the argument in how to push back on unrealistic deadlines.
Two estimates worked through end to end
An 18,000-word manual with a Thursday request
A client sends a 60-page technical manual, English to German, 18,400 words, already machine pre-translated, and asks for Thursday. It is Monday.
From the log: full post-editing of technical DOCX runs 1,100 words an hour at the slow end, so 17 hours of post-editing. File prep, because the tables arrived as nested boxes and the warning callouts lost their formatting, 1.5 hours. Glossary assembly from the client's earlier files, 1 hour. QA pass plus fixing what it flags, 3 hours. Formatting pass, since German runs longer and the tables will reflow, 1.5 hours. Delivery and cover note, half an hour.
Effort: 24.5 hours. Free capacity this week after existing commitments: 11 hours. The honest answer is not Thursday. It is the following Tuesday.
That is where the conversation starts rather than ends. You can offer the body of the manual on Thursday and the three annexes on Monday, which is often what the client needs anyway because the annexes go to a different reviewer.
A deck and a price list in two days
Monday afternoon: a 58-slide PPTX plus an XLSX price list, English to Spanish, wanted Wednesday.
The deck is 3,100 words on the slides and 1,900 in the speaker notes. Post-editing at 900 words an hour, 5.5 hours. The workbook is 1,400 words across 900 cells, and at the 350 words an hour that fragment work runs for us, that is 4 hours rather than the 1.5 the word count suggests. Spanish expands against English, so slide text boxes will overflow and need resizing, 2.5 hours. QA, number and currency checks, delivery, 2 hours.
Effort: 14 hours across Tuesday and Wednesday, with no room for a single query. So you split it. The deck on Wednesday, because that is what they are presenting from, and the workbook Thursday morning. Phased delivery beats one date you will miss.
The ten-minute estimate you can run before you reply
Before you send a date, do this. It takes ten minutes and it is the difference between a date and a hope.
- Open the file. Not the email, the file. Check the format, the condition, and whether text is hiding in speaker notes, headers, footers, hidden sheets or embedded objects.
- Count it yourself. Counts you are sent are often wrong, and PDF counts are wrong in both directions.
- Pick the throughput range from your log that matches this document type and this kind of work, whether from scratch or MTPE, and use the slow end.
- Add the non-translation steps as hours, item by item: prep, references, QA, the fix loop, formatting, delivery.
- Add the query round as calendar days, based on how fast this client actually answers rather than how fast they should.
- Look at what is free in your week, not at what forty hours would allow.
- Set the internal date, then add a night of sleep to get the client date.
- Say the date with its assumption attached, and say what you will do if the assumption breaks.
If step six tells you the honest date lands later than the one they asked for, you have three real options: deliver in phases, cut the scope down to what genuinely needs publication quality, or say no. Guessing a date you cannot hold is not on that list, even though it is the one that feels easiest on Monday morning.